Status as of November 29th.
The weather report is calling for snow in Karuizawa today, but in spite of the cold temperatures, construction is moving right along on ISAK’s facilities.
Dormitory and Faculty Housing: Timber framing work underway
School Building: Foundation work complete
Gymnasium: Steel framing work underway